Saturday, February 25, 2012

Next Work Day For Habitat Volunteers

Good Morning, Habitat Volunteers:

Our next workdays will be: Thursday, March 1st, 2012 and if need be, Friday, March 2nd, 2012. We will be hanging the drywall on the ceiling. If you can help us with this part of the work, please plan to start about 8:00 a.m. You will need to bring lunch with you. To make it easier, we will be using drywall lift jacks.

The rough electric has been completed and will be inspected by Code Inspections hopefully on Monday or Tuesday. This inspection will then allow us to work on the ceiling drywall. Once the ceiling drywall is complete, we will have the insulation work done by Dave Saulter.

There are several other areas of the house that can be worked on:
Start to install the heating system
Finish the rough plumbing
Run the gas line

Thank you again for your help as a Habitat Volunteer!

Jim and Charlotte Blain
jrcmblain@aol.com